Costco Wembley

 

Principal contractor
JF Finnegan

Duration
32no weeks

Project value
£2.9 million

Scope of Works

  • Section 278 works, groundworks and external works including hard landscaping.

  • We were originally just appointed for the initial enabling works associated with the Section 278 works. However, because of our performance, Finnegan negotiated a substantial amount of additional works. 

  • Groundworks associated with the construction of the main store. This included extensive deep drainage, pad foundations and infrastructure works. 

      

GroundworksLuke Davies