Shurgard Herne Hill

 

Principal Contractor
Appian Construction 

Duration
32 weeks

Project value
£2 million

Scope of Works

  • Form waterproof basement

  • Reduce level basement dig

  • Form RC guide wall 

  • Seacant Piled Wall 

  • 8000m3 Basement Dig

  • RC basement pad foundations

  • Drainage/Services

  • 3m single sided fair faced liner wall

  • Basement power floated slab

  • External works 

BasementsLuke Davies